December Hurricane Patricia Update

We are pleased to announce that we completed the hurricane shelter installation at our second elementary school in the village of Miguel Hidalgo Viejo on December 18. We have almost finished the panels for our third school in the village of Arroyo Seco, which we expect to be completely installed by the end of the second week of January. At that point, we will begin work in the villages of Miguel Hidalgo Nuevo and San Mateo. As always, our progress is much dependent on the government completing their obligatory repairs at each school, as we cannot begin working until this has been completed.